Dacopan project                                MEETING MINUTES
                                               May 3rd, 2004

Meeting
        May 3rd, 2004, at 12:15

        Department of Computer Science,
        State University of Petrozavodsk,
        Room 138

Attendance
        Alejandro Fernandez Rey
        Carlos Arrastia Aparicio
        Jari Aarniala, secretary
        Jarkko Laine
        Jonathan Brown, chairman
        Turjo Tuohiniemi, instructor
        Vesa Vainio

        Andrei Ananin
        Dmitry Korzun, instructor
        Kirill Kulakov
        Mikhail Kryshen
        Viktor Surikov

        Inkeri Verkamo

Absent
        Andrei Salo


1. Start
        Mr. Brown started the meeting at 12:15


2. Assessment of the situation
        This is the first global meeting since February. Both teams have almost
        finished implementing their subsystems. Integration testing can start.
        
3. Discussion
        It was decided that for the duration of the H-group's stay in Petrozavodsk,
        a local CVS repository will be used. The contents of the repository can be
        transferred back to the main repository when H-group leaves Petrozavodsk.
        Mr. Tuohiniemi has a USB memory stick that can be used to take a backup copy
        of the data.

        P-group has finished implementation phase and is in process of finalizing
        their local integration today or tomorrow (May 4th). PEF files can already
        be output, but some problems exist. However, the integration testing of both
        systems can start without any "real" data from the Analyzer.
        P-group will divide in to two groups: one responsible for
        documentation and one for integration testing.

        Mr. Tuohiniemi pointed out that integration tests need to be specified in
        the test plan and their execution in the test execution document. Mr. Vainio
        reminded us that user interface tests are hard, if not impossible to automate
        so that they can be run periodically without human intervention.

        The Analyzer can currently print out PEFs for six different scenarios, although
        these scenarios are contained in only 3 separate PEF files.

        For H-group, implementation and integration testing can continue at the same
        time, but focus should be kept on good quality (i.e. testing, squashing bugs)
        instead of introducing new features other than those already designed.

        For documentation, a user manual should be written. Also, the design document
        should be updated to correspond the current state of design.

        Localization of the Animator will be done during the next two weeks. It is
        trivial technically, but writing the translations might require some hours'
        worth of work from both teams.

        
4. Action points
        - Next meeting on Thursday May 6th at 3:15pm in room 138.
        - Whole team should be present on Wednesday, as we can expect
          high-level visitors to our project room.
        - Start integration testing
        - Check the status of localization on Thursday
        - Planning of integration tests can start already even without
          PEF files by looking at the scenario -section of the requirements
          document.

            
5. End
        Mr. Brown ended the meeting at 13:00